Liquefaction Project Schedule
July 26, 2010 Submitted NEPA Pre-Filing Request
August 4, 2010 FERC Approval to use Pre-Filing Process
January 31, 2011 File NGA Section 3 Application
2H - 2011* Issuance of Environmental Assessment / Environmental Impact Statement
2H - 2011* Issuance of Authorization
2H - 2011* File Initial Implementation Plan
1st Q - 2012* Commence Construction
2015* Liquefaction Project In-Service

*dates are estimates and are subject to change


 