Liquefaction Project Schedule
July 26, 2010
Submitted NEPA Pre-Filing Request
August 4, 2010
FERC Approval to use Pre-Filing Process
January 31, 2011
File NGA Section 3 Application
2H - 2011*
Issuance of Environmental Assessment / Environmental Impact Statement
2H - 2011*
Issuance of Authorization
2H - 2011*
File Initial Implementation Plan
1st Q - 2012*
Commence Construction
2015*
Liquefaction Project In-Service
*
dates are estimates and are subject to change