Liquefaction Project Schedule
July 26, 2010 Submitted NEPA Pre-Filing Request
August 4, 2010 FERC Approval to use Pre-Filing Process
January 31, 2011 File NGA Section 3 Application
December 28, 2011 Issuance of Environmental Assessment / Environmental Impact Statement
January 31, 2012 File Initial Implementation Plan
April 16, 2012 Issuance of Authorization
3rd Q - 2012 Commence Construction
4Q 2015* Liquefaction Project In-Service

*dates are estimates and are subject to change

 

 

 
 